2001 ACE AWARDS

 

 

CATEGORY #14

                                                            Meeting the Challenge of a Difficult Job

            Subcontractor

 

                                                            PROJECT

                                                            A Computer Chip Manufacturing Facility

                                               

                                                Owner

                                                            Not to be disclosed due to Non-Disclosure Agreement

 

                                                            General Contractor

                                                            DPR Construction, Inc.

 

                                                            Architect/Engineer

                                                            Jacobs Engineering

 

                                                            Electrical Subcontractor

                                                            Ludvik Electric Co.

 

                                                           

 

 

 

                                                            Submitted By:         Ludvik Electric Co.

 


LUDVIK “INSIDE”

In the Spring of 2000, Ludvik Electric Co. was contacted to participate on a design assist basis to complete the construction of an existing manufacturing plant and add necessary infrastructure, buildings and systems to support a 1,757,300 sq. ft. project consisting of 728,000 sq. ft. Manufacturing; 165,400 sq. ft. Class 1 Cleanroom; 26,100 sq. ft. Utility Building; 82,800 sq. ft. Process Support; 265,000 sq. ft. Test/Lab; Process Gas Yards; 450,000 sq. ft. Office Building; and a 40,000 sq. ft. Warehouse Building.  The schedule was 15-months for completion, a record pace even for this client.

            Ludvik immediately mobilized a staff to meet with the client on design and construction parameters and simultaneously dispatched field crews to determine existing conditions as the plant had been mothballed for several years.  Demolition of old and addition of new infrastructure improvements began immediately while design was developed.  The original plan to complete the existing facility was quickly discarded and a total upgrade was pursued as this client’s process was too sophisticated to be supported by the existing plant.

            Recognizing this change would vastly affect the project and therefore the management approach, Ludvik modified its plan.  With the work plan now indicating the need to put in place approximately 1,300,000 man-hours of work in approximately 12 months (i.e. 3 months design, 12 months construction), an organization was established to provide one overall Construction Manager, supported by four (4) Project Managers, four (4) Project Coordinators, two (2) Estimators, two (2) Schedulers, five (5) Quality Control Managers, eight (8) Safety

Managers, five (5) Field Engineers, nine (9) Accounting Personnel and two (2) Clerical Support.  A later change in site requirements to move all material offsite rendered the addition of ten (10) full-time Material Storage and Lay Down Yard to be added to the mix.

            The work plan, now showing a peak workforce of 850 Electricians, presented a new issue.  Where do we find 850 Electricians in Colorado’s booming economy?

            Ludvik immediately reinforced its Human Resources Department who undertook to contact every NECA Chapter and every Local Union in the Nation.  Not relying on that source alone, the HR Department also put on an extensive radio and TV blitz as well as mass mailings, newspapers, trade publications and internet searches to attract the needed manpower.  Incentives were established to help attract and retain new hires so that learning curve losses would be minimized.  In all, over 1,800 craftsmen were interviewed and offered employment.

            To insure proper supervision of the workforce, 88 Foremen were put through Ludvik’s Supervisory Training Program.  Training was provided at the craft level as many unique situations present themselves in clean room construction.  An industry construction expert was retained to review all levels of operations at the site and make recommendations.  This program was so effective, immediate productivity improvements were noted in Ludvik’s studies.          

 As a safety issue, the client had required daily calisthenics, known as Stretch and Flex, to be conducted before the start of each shift.  An Orientation Program was developed for each and every employee at the site.  Pre-Task Planning and a Hazard Awareness Program were initiated to keep the tradesmen appraised of

related hazards in their work areas.  Ludvik endeavored to maintain one safety professional for every 50 tradesmen during the duration.  The results of this are a 1,340,000 man-hour project executed without a lost time accident. 

            Ludvik initiated an electronic filing system on the project to help administer the projects.  In all, 28 computers were installed at the site interacting with the home office through T-1 lines.  Approximately 85,000 documents were managed with full and immediate access by personnel in real time.

            The 1,800 electrical drawings, that were eventually prepared, were reissued an average of four times creating an estimating, budgeting and material purchasing task never previously experienced at Ludvik.  Full-time estimators, at the jobsite supported on several occasions of high activity by the corporate staff, created each of the multitude of estimates required by the client.  Every scenario had a complete budget and material purchase uniquely associated with the activity.

            To insure Ludvik was dispatching its workforce and resources to the proper tasks, an electrical schedule was prepared containing 2,000 activities, each with four subsets.  All task, with current activity, were updated weekly with critical areas updated daily.  These efforts allowed actual progress on the electrical portion of construction to never negatively effect the plant completion.

            This project presented many exciting challenges, each of which was met with detailed analysis and creative remedies.  With Ludvik “Inside”, you can be assured of dedicated efforts toward a successful completion.