1999 ACE AWARDS
CATEGORY #9
Project
Of The Year (Over $6 Million)
Subcontractor
PROJECT
National
Oceanic and Atmospheric Administration (NOAA)
Scientific
& Research Center
OWNER
General
Services Administration
GENERAL CONTRACTOR
Hensel
Phelps Construction Co.
ARCHITECT
C.W.
Fentress, J.H. Bradurn & Associates P.C.
ENGINEERS
Garland
Cox & Associates
Riegel-Doyle
BCER
Consulting Engineers
SUBMITTED BY
Ludvik
Electric Co.
A
FLOOD OF OBSTACLES AT NOAA
With science and technology advancing at an exponential
rate, the National Oceanic and Atmospheric Administration (NOAA) found that its
office, laboratory and research facilities were obsolete for meeting their
needs. A new $50 million, 372,000-square-foot, state-of-the-art facility was
authorized for construction in Boulder, CO. The huge complex is known as the
David Skaggs Research Center and consists of four buildings and a central core.
It is 900 feet in length, up to 165 feet in width by 43 feet in height and
provides space for over 1,000 scientists, researchers and staff personnel. The
4-story facility (including a garden level partially below grade) houses six
laboratories that make up NOAA's Environmental Research Laboratories (ERL), two
data centers for the National Environmental Satellite, Data and Information
Service (NESDIS), the National Geophysical Data Center, the local office of the
National Weather Service, and the Mountain Administrative Support Center. Also
part of the complex is a remote solar observatory that is located 1,500 feet
away. From these facilities comes everything from tornado alerts to studies on
marine geology and geophysics to information on solar flares. High-tech stuff.
Getting the sophisticated, extremely complex facility
"connected" was a challenging assignment for Ludvik Electric. The
scope of our electrical work encompassed all electrical systems including a
state of the art tele/data network consisting of fiber optic and Level 6 cabling for voice and
data—the first application of this
300 MHz copper cable anywhere. The installation also included:
• Two 3000 amp
services and distribution as well as a 1200 kW generator and a 150 kW generator
for emergency and standby power
• Installation of
a variety of special building systems including lighting with a sophisticated
control system and motion sensors, fire alarm, card access security, paging,
lightning protection, site lighting and an extensive amount of lab wiring
With a complex plan
well underway for relocating more than 1,000 people from other NOAA locations
to the new facility, hitting the move-in date was of paramount importance. The
complexity of the project and the installation of a never-before-used data
cable presented major challenges for Ludvik. And, ironically, it was the
weather that contributed one of the biggest obstacles along the way.
A few numbers will tell you the story about the
complexity of this state-of-the-art building. Ludvik installed 250,000 feet of
conduit in the poured-in-place 8-inch concrete slabs and 6,677 feet of custom
laboratory raceway configured to meet the power and tele/data requirements of
individual scientists. In addition, the entire building had 6-inch raised
floors. There was 350,000 feet (66 miles) of Category 5 phone cable, 315,000
feet (59 miles) of fiber cable, and 560,000 feet (106 miles) of the Level 6
data cable. There were 5,536 light fixtures, over 5,000 power outlets (evenly
split between conditioned and non-conditioned depending on scientific needs),
and 1,365 Standard Information Outlets (SIO). SIOs originated from one of 44
Immediate Distribution Facility (IDF) rooms located throughout the complex.
Each SIO required two telephone, two Level 6, and two 4-strand fiberoptic
connections. Ludvik custom fabricated special whips for the under-floor
connection. These customized whips enabled Ludvik electricians to precisely
position boxes according to individual office layout requirements while
allowing flexibility for future reconfiguration.
The use of the new Level 6 data cable required some
special procedures. In response, Ludvik sent two Project Supervisors and the
Project Manager to the manufacturer's plant in Hickory, South Carolina, for a
2-week certification course. They were schooled on the ins and outs of handling
and installing this leading edge product—everything from shipping to bending
radius limitations to termination. This extra effort prevented damage and
guaranteed a quality, trouble-free installation.
The Solar Observatory presented another unique problem
for Ludvik. The building has the same sophisticated phone, power and tele/data
requirements as the main complex. Wire and cable were run through an
underground ductbank from the main facility. But getting it there proved to be
a unique
adventure. Because of the close proximity of ancient Native American burial
grounds that could not be disturbed, extreme care had to be taken in trenching
for the duct. Compounding the problem were boulders up to 15 feet in diameter,
both in the path and underground, as well as existing underground sewer and
water lines. Rather than routing hundreds of feet out of the way (at great
expense), the Ludvik solution was to move the boulders with D9 tractors and use
them as natural landscaping—all under the watchful eye of a tribal chief.
Ironically, it was the weather that contributed the
biggest problem on the job. With over 90% of the electrical installation
complete, one of the area's infamous flash floods inundated the garden level!
Ludvik had no alternative but to remove all installed wiring. The flood's silty
residue required that all conduit had to be flushed, blown out, treated with
antibacterial chemicals, and dried before re-pulling the wire. Installed boxes
and other electrical devices that were affected also had to be removed or
cleaned, treated and dried where possible. This was necessary to insure there
was no chance of a "sick building syndrome" that could possibly
affect the health of workers in the future. Despite the setback, the completion
date could not be changed. To address the problem, Ludvik secured additional
electricians and authorized whatever overtime hours it would take to complete
the monumental task. Meanwhile, to meet the non-negotiable move-in date, work
proceeded on other levels of the building according to schedule—it was like two
projects in one!
In addition to its regular comprehensive safety program,
the flash flood is a reminder of the special safety precautions Ludvik's Safety
Director initiated on the project. The building's proximity to the foothills
called for special attention to hazards posed by strong winds, lightning and
severe storms. Safety meetings included recognition of threatening weather and
placed added emphasis on fall protection. Despite more than 110,300 man-hours,
Ludvik experienced no lost time due to accident or injury.
A complex high-tech electrical installation, innovative
materials, and a flood of obstacles to work around—Ludvik handled it all for
NOAA and 1,000 people moved in on time!