1999 ACE AWARDS
CATEGORY #13
Meeting
the Challenge of a Difficult Job
Subcontractor
PROJECT
J.D.
Edwards Office Building III
Backup
Generator Farm
OWNER
J.D.
Edwards Corporation
GENERAL CONTRACTOR
Hensel
Phelps Construction Co.
ARCHITECT
C.W.
Fentress, J.H. Bradburn & Associates P.C.
ENGINEER
Ludvik
Electric Co.
RMH
Group
SUBMITTED BY
Ludvik
Electric Co.
4.5 MEGAWATT GENERATION PLANT
PROVIDES NO COMPROMISE ON POWER AT J.D. EDWARDS III
With more than 5,000 clients located in 100 countries, J.D.
Edwards is at the forefront in developing, marketing and supporting computer
solutions for supply chain efficiency. Their integrated solutions for
manufacturing, distribution, finance and human resources combine with a
flexible technology architecture to help clients "put ideas into action with unprecedented control." Part
of that commitment means the availability of critical services and support 24 hour a day, 7 days a week, 365 days
a year, anywhere on the planet. An outage, a blip, a glitch, a spike in
power could mean certain disaster for some client somewhere. And that's where
the story of this difficult challenge began for Ludvik Electric.
J.D. Edwards III, a design-build project, is a
196,650-square-foot, 6-story, high-tech office building with a full basement
and adjacent 4-level parking structure. It is the third of eight buildings that
make up the company's Corporate Headquarters campus in the Denver Technological
Center. Building III, however, houses the critical tele/data systems that
support and connect it with clients worldwide—literally the heart of J.D.
Edwards. The lower and first levels contain the Corporate Data Center and
Computer Labs, all on raised computer floors. A scheduled move-in date could
not be missed.
Ludvik's electrical construction on the building called
for two (2) 4000 amp services, power distribution and mechanical equipment
connections, outlets and electrical devices, lighting, tele/data cable tray, a
fire alarm and detection system, and a small generator and UPS for minimal
power to emergency lighting, one elevator, fire alarms and the security system.
A complex but routine assignment.
But then, with the building less than five months from
completion, a whole new and separate project was thrown into the mix. J.D.
Edwards concluded that the critical services and support emanating from
Building III could not be compromised. The original backup power system was not
adequate. They needed 4.5 megawatts
of 100% foolproof backup power capability. The resulting system
was comprised of three 1500kW backup generators and five UPS battery banks!
Literally overnight, a job of monumental difficulty was put on the table,
challenging Ludvik's skills and resourcefulness to the limit.
A generator farm had
to be added to the site. But space was limited on the campus and there was no
provision for such a facility. The farm would have to contain three
25,000-pound Cummins V-16 supercharged diesel generators, a 10,000 gallon tank
that would hold approximately 38,000 pounds of fuel, and a sophisticated
switchgear measuring 30' x 6' x 7' weighing 52,000 pounds. Working closely with
the architect and J.D. Edwards, Ludvik identified an area adjacent to the
parking structure as the only possible location for the farm. One problem faced
immediately was the confined space available due to the architectural design on
the building and proximity of a public sidewalk and street. Ludvik's solution
was to position one of the generators at a 90° angle to the other two. It was a
tight fit, but it worked.
Ludvik engineers headed for Higgam, Massachusetts,
headquarters for Russelectric, a manufacturer of high integrity power
protection and control systems for critical facilities. It was September 9. In
less than 24 hours, a unique open-transition
transfer parallel switchgear was designed to meet the needs of the
facility. It contains a main switch, a control section, three generator
sections, breakers, fault detectors, synchronizers and other gear. This rare
equipment configuration provides an effective solution to the problem of
momentary power fluctuations, which could prove disastrous for J.D. Edwards and
its clients. By matching sine waves and controlling generator rpm, the system
synchronizes the transfer from auxiliary power to utility company power. It
senses the voltage, frequency and phase relationship of both sources and allows
a transfer only if the two sources are within acceptable limits.
Meanwhile, back in Denver the generator farm site was
prepared. Several problems had to be overcome. To keep the equipment out of
sight and baffle sound, the foundation was sunk four feet below grade and an
architecturally compatible perimeter wall was built. Caissons were poured to
support the weight of the generators and fuel tank. A 24-inch slab completed
the foundation structure. The switchgear was enclosed in a room built at the
end of the space. Conduit was installed.
Concurrently, inside Building III's UPS room, a large
rack (35' x 8' x 5.5') was built for five UPS battery banks—two 225 KVA systems
and three 150 KVA systems. These systems would provide instantaneous auxiliary
power in the event of a utility power failure while the backup generators were
coming online. Filling this 17-second gap was critical in meeting J.D. Edwards
uninterrupted power needs.
By December 1, the switchgear was ready for testing at
Russelectric's Tulsa, Oklahoma, manufacturing plant. After the successful test
results, the equipment was shipped to Denver, arriving on December 7.
Installation proceeded immediately. The Cummins generators arrived on December
29, right in the middle of the holiday season. Regardless, the intense project
had to proceed to stay on schedule. On January 23, the installation was
complete, the generators started, and testing began. It had all been accomplished in 4-1/2 months, from
system concept to startup!
Coordination of the generator farm project required
ongoing contact between Ludvik, consulting engineers, equipment manufacturers,
architects, J.D. Edwards and Public Service Company of Colorado. Everyone was kept
"in the loop" to insure the integrity of the system and its
performance. The system is capable of providing 100% uninterrupted, perfectly
conditioned power for 48 hours for all Building III systems—indefinitely with
refueling. A Programmable Logic Controller automatically determines power
requirements and coordinates the transfer between utility and auxiliary power.
To provide J.D. Edwards with a high comfort level, power in Building III is
transferred to the auxiliary generators for 30 minutes every Saturday
morning—seamlessly and without interruption to their critical operations.
The installation of large, heavy equipment during the
winter season, the intense testing program, and the short schedule called for
special attention to safety. Ludvik's uncompromising safety program, inclu-ding
fall and hearing protection, resulted in no lost time accidents on the
generator farm installation.
A difficult challenge met through uninterrupted effort
and cooperation by everyone on the job!