1999 ACE AWARDS
CATEGORY #6
Project
Of The Year (Under $1 Million)
Subcontractor
PROJECT
Celestica
Colorado Office/Manufacturing Facility
OWNER
Celestica
Canada Inc.
GENERAL CONTRACTOR
DPR
Construction Inc.
ARCHITECT
Young
& Wright Architects Inc.
ENGINEER
Carinci
Burt Rogers Engineers Inc.
SUBMITTED BY
Ludvik
Electric Co.
On
A Fast Track To Production At Celestica
It's no secret that competition in the world of
electronics manufacturing—personal computers, telecommunications equipment and
anything with a circuit board inside—is nothing short of fierce. Prices
continue to free-fall to such a degree that some products that once sold for
thousands are now going for a few hundred dollars—or less! This intense battle
for sales and market share is putting tremendous pressure on OEMs to lower
costs and maximize efficiency.
Celestica Inc. is one company with a solution. It's
called contract electronics
manufacturing, or CEM for short, whereby outside contractors like
Celestica handle manufacturing and assembly tasks for OEMs while they focus
their efforts on design, marketing and product support. Celestica's customers
include Hewlett-Packard, Apple Computer, IBM, Lucent Technologies, Digital
Equipment and Gateway—an impressive list to say the least. A global leader in
this new and rapidly emerging CEM business model, Celestica recently moved its
Colorado operations into a new, state-of-the-art, 209,000-square-foot facility
in Ft. Collins.
Ludvik Electric performed the "fit-up" phase of
the electrical installation. The project consisted of: 1) power distribution
and data systems for 117,300 square feet of manufacturing area which included
seven separate production lines; 2) lighting and power systems for 33,000
square feet of warehouse area and 58,700 square feet of office space; and 3) a
CCTV security system for the entire facility.
The project could seem routine until you consider the
challenges that confronted Ludvik in this new CEM environment and how each was
overcome.
• Each of the seven production lines was
customized for a specific Celestica customer, requiring different power and
data needs. Each line entailed a unique combination of cable tray, conduit,
panduit, wire mold and circuit configurations to accommodate robotics, solder
ovens, test stations and other high-tech manufacturing and assembly
paraphernalia. A rolling 3-week schedule was implemented by Ludvik to insure
that required materials for each line were available and on site as needed.
• The installation was on an extremely fast track, with
Ludvik having to complete its work in less than four months. Celestica was
moving from an existing facility into the new one. Any deviation from their
planned manufacturing downtime would have meant a catastrophic setback for
Celestica customers. In spite of a regional manpower shortage, Ludvik was able
to assemble a peak crew of 60 journeymen. Five 10-hour shifts were scheduled at
the beginning of the project, six 10's were scheduled as the work neared
completion to insure that the job was completed on time.
• The production lines were installed
sequentially. As each line was completed, a specific customer began operations.
This created an unusual situation where construction
and production were occurring simultaneously—now under a semi-cleanroom
protocol. In addition to donning gowns, Ludvik had to insure that the work site
was clean and free of static electricity, affecting the handling and operation
of everything from tools to scissor lifts used to install conduit in ceilings
as high as 45' above the floor. In addition to their regular construction
safety training, Ludvik personnel were also trained in process safety
management for a better understanding of the production operations going on in
close proximity to their own work, including the use of various chemicals,
ovens and robotic equipment. While Ludvik personnel spent approximately 30,400
man-hours on the project, there were no lost time injuries.
• Special
materials required on the project included such devices as 200% neutral
bus plugs to provide more stable power to production line equipment. These
plugs required 6- to 8-week order lead times. To guarantee that these and other
items would be available when needed, a JIT, next-day-delivery materials
procurement and handling program was initiated by Ludvik, headed by a full time
supervisor.
• Typical of the computer industry, the technology changes literally by
the week. The result was a dynamic environment as customer equipment and
process needs evolved, even as the installation was in progress. Throughout the
installation, a complete set of current drawings was never available. During
the installation of individual production lines, equipment literally became
obsolete overnight and had to be removed and replaced with the up-to-the-moment
technology. Despite the myriad of change orders, Ludvik's scheduling and
materials procurement programs kept the installation on track and on time
throughout.
• The core-and-shell portion of the electrical
work was being performed by a separate electrical company, resulting in overlapping installations and
complicating project coordination. Coordination meetings proved essential for
Ludvik in the efficient and timely electrical installation for the individual
production lines. Composite CAD drawings were used to determine exactly where
and when various electrical, mechanical, fire, security and architectural items
were to be installed. Regular weekly coordination meetings of all subcontractor
foremen were supplemented with daily 8:00 am meetings to address specific
design and installation issues.
The seven production lines included in the base scope of
the project were completed on time and on budget and Celestica's customers all
began operations on schedule. Ludvik has been retained to install three
additional production lines. And, under a maintenance agreement with Celestica,
Ludvik will continue to update and modify existing lines as customer needs
change—all in a facility that could balloon to 600,000 square in the
not-too-distant future.
Overcoming a fast-track schedule and the unusual
construction/production environment at Celestica's new facility, Ludvik brought
their customers' production lines online, on time, every time!