AT&T Critical Power
System Upgrade

1997 ACE AWARDS
PROJECT
Critical Power System Upgrade
CATEGORY #1
Project of the Year Under $2 Million
Prime Contractor
OWNER
A T & T Corporation
PRIME CONTRACTOR
Ludvik Electric Co.
ARCHITECT
MCB Architects
ENGINEER
Cator, Ruma Engineering
SUBMITTED BY:
Ludvik Electric Co.
WORKING THROUGH A SMALL WINDOW OF OPPORTUNITY
AT AN AT&T PLATINUM FACILITY
Communication over telephone lines has dramatically changed over the past decade. New long distance services. Modems. E-mail. Faxes. The Internet. Demand for phone lines is at an unprecedented level and growing. Long distance isnt just for calling grandma anymore.
Long distance leader AT&T operates a network feeder and carrier facility near Mead, Colorado that gives a new definition to the word "critical". Approximately 45% of the long distance traffic between the Midwest and the West Coast passes through this facility. A failure of any kind could be disastrous for customers and cost AT&T as much as $5 million per hour in long distance revenue. Obviously, reliable electric power is vital to the facilitys operation.
WHAT AT&T CALLED FOR

A T & T needed to upgrade the facilitys critical power system. The competitive-bid hard-dollar project involved removal of two old, undersized backup power generators and controls and installation of two new parallel and redundant Onan/Cummins generators with state-of-the-art Programmable Logic Controls. Seems simple enough. But . . .
This was anything but a simple, everyday, routine installation.
LUDVIK HAD THE ANSWERS
To provide access, Ludvik first had to create an opening by removing the air duct intake grating and louvers between the basement generator room and the shaft leading to the roof. A catwalk in the shaft also had to be removed to clear the way for passage of the generators. While the shaft reached the roof, it had been sealed by a 19,000-pound "removable" panel, which had then been roofed over. The panel was located and the roof cut around it, enabling it to be lifted out. This created the only possible opening through which old and new equipment could be conveyed. Since it was the rainy season, a curb was built around the opening and a "shoe box" type removable lid was fabricated to cover it temporarily (and permanently once the project was completed).
Meanwhile, Ludvik was working closely with AT&T and its consultant on specifications and delivery of the new custom-built generators. Because timing was critical, the usual 16-week procurement process was reduced to 10 weeks, thanks in part to a strong working relationship between Ludvik and the regional Onan/Cummins distributor. A target delivery date was identified and committed to by the manufacturer.
While the project required weeks of planning, the real work took place within a matter of hours. As prime contractor, Ludvik coordinated the activities of all trades including electrical, roofing, crane, sheet metal, mechanical and automation controls. Weekly schedule updates and construction meetings insured that everything and everyone was prepared for the installation window. Teamwork was essential to the success of the project. Ludvik prepared a Special Method of Procedure (SMOP) for every step of the process, detailed to 15-minute intervals. Everything had to work. There was no room for error, no way to rehearse!
Finally, right on schedule, the "window of opportunity" arrived. A temporary external backup generator that matched the buildings features was tied in just in case of power failure. After disconnecting the old generators, a system of dollies and chains was employed to pull them out of the generator room and lift them up through the shaft. The "easy" part.
The next day, the new 12,000-pound 14 x 6 generators went in. To lower them down the 18 x 18 shaft and turn them into the generator room, they had to be tilted at a precise angle of 70 degrees, lowered through the exhaust shaft, and then turned 90 degrees to fit into the access hold. The tolerance was a matter of degrees and inches as the generators barely fit in the shaft. It was trial and error all the way down. But a specially configured system of chains and rollers, along with a well-thought-out plan for lowering the huge pieces of equipment, got the job done.
The first generator was in place five hours. The second took only 1.5 hours. What was planned only on paper and in theory had worked! The parallel generators, one the prime backup and the other a secondary backup, were tied into the buildings electrical system, programmed and debugged. The usual 30-day testing and commissioning process was accomplished in just five days working from midnight to 6:00 a.m.
DIRECT LINE TO SAFETY
The unusual nature of the installation required unusual attention to safety. Orientation meetings, safety audits and special training sessions educated all trade workers on issues including confined spaces, ladders, power actuated tools, hoist and lift operations, fall protection, tripping and dust hazards. The sensitive environment often meant that personnel had to work in stocking feet, requiring specially designed tool pouches. Non-conductive dielectric tools were also required. Result: no lost time accidents during 2,000 hours spent on the job.
When AT&T called for a unique installation, Ludvik answered and continues to perform all electrical work at this AT&T Platinum facility.