It was determined in short time that the project would require approximately 1,300,000 man-hours for completion in 12 months on Focusing on safety for all resulted in a successful 1,340,000 man-hour project without a lost-time accident. The 1,757,300sq. ft. High Tech campus included: •728,800sq. ft Manufacturing Building •165,400sq. ft Class 1 Clean Room •26,100sq. ft. Control Utility Building •82,800sq. ft. Process Support Building •265,000sq. ft Test/Lab Building •450,000sq. ft. Office Building •40,000sq. ft. Warehouse Building •Parking Structure AGC of Colorado awarded Ludvik Electric a 2001 ACE Award for this project General Contractor: DRP Construction Computer Chip FAB Plant.
The project included both the chip manufacturing facility and the tool buildout.
this fast-track project. The Human Resources Department immediately embarked on a nationwide recruitment effort for
dedicated, trained and experienced personnel.